Energy Audit - A Definition as per Standard
According to DIN EN 16247-1, an energy audit is a systematic inspection and analysis of the energy use and consumption of a plant, building, system or organization, with the aim of identifying and reporting on energy flows and the potential for energy efficiency improvements.
The goal is to identify energy flows and the potential for energy efficiency improvements. The next step is to assign a monetary value to various measures through investment and economic efficiency studies, so that ROI can be worked out by companies.
As per ISO 50001:2018, Clause 3.14, Energy Audit is also defined as:
An energy audit is a systematic, documented process to obtain sufficient information about the energy performance of an organization and identify opportunities for improvement of the energy performance, in addition to other relevant environmental and financial information.
Other Services
Q Sine offers power quality enhancement & power continuity solutions

Annual Maintenance Contracts
We offer our specialised services for the equipment of various Brands and Makes.

Power Quality Audit Service
Q Sine specialises in conducting PQA and makes analysis of the data. Based on which the solution is worked out.
Industries we serve
Manufacturing
Automobile
Foundry
Hospitals
Packaging
Sugar Mills
Pharma
Datacenters
Textiles
FMCG
Agro Industries
Metal, Mineral & Mines
Case Studies
Sandvik Asia, Pune (End User)
- Load Details : Industrial machines
- Before condition : Initially Current THD was observed to be 15%.
- Solution / Proposal : Proposed 100 Amp AHF - 2 units
- After Solution : Current THD reduced to 6%
Sagar Manufacturers Pvt Ltd (SMPL), Bhopal
- Load Details : Spinning mill machines
- Before condition : Initially Current THD was observed to be 15%
- Solution / Proposal : Proposed 150 Amp AHF - 5 units and 300 Amp AHF - 6 units
- After Solution : Current THD reduced to 7%
Fresenius kabi India Pvt. Ltd, Pune
- Load Details : Machines Application (Pharma)
- Before condition : Power factor was a major concern which was about 0.97
- Solution / Proposal :Proposed 510 KVAR Hybrid panel with 400 KVAR RTPFC & 110 KVAR lead / lag step less power factor correction ( SVG ) Panel
- After Solution : PF improved to 0.995
Sampada Paper Mill, Sangli
- Load Details : Craft paper mill machines
- Before condition :Initially Current THD was observed to be 18% & VTHD 3.2%
- Solution / Proposal : Proposed 200 Amp AHF unit
- After Solution : Current THD reduced to 7% & VTHD reduced to 2.5%
Yash Industries Maharashtra
- Load Details : CNC machines
- Before condition : Power factor concern
- Solution / Proposal : Active correction of PF by SVG
- After Solution : PF improved to 0.995
Kisan Agro, Maharashtra
- Load Details : VFD and motors
- Before condition : Harmonics & Power factor concern
- Solution / Proposal : Active correction of PF by SVG and Harmonics by AHF
- After Solution : PF improved to 0.995 & met IEEE 519:2014 standard for Harmonics